EnCana Ekwan Pipeline Project (December 2003 – March 2004)

Owner: EnCana Ekwan Pipeline Inc.
Superintendent: Bill Porter

The high profile EnCana Ekwan Pipeline Project was constructed in northeastern BC and northwestern Alberta under NEB (National Energy Board) jurisdiction.

Project Highlights:

  • 82,300 metres of 24-inch mainline
  • 335,000 total project man hours
  • Labour force peak of 315
  • Working partner of the Fort Nelson First Nation and the Dene Tha’ First Nation
  • Zero lost time incidents
  • Zero NEB notices
  • Substantial completion was nine days ahead of schedule