CLIENT NAME: TransCanada

PROJECT NAME: Lateral Loop No.3

LOCATION: Chinchaga Area, Alberta

SCOPE: 33,200m of NPS 48

PEAK PERSONNEL: 440

Surerus was the prime contractor for the installation of 33,200m of NPS 48 steel pipe northwest of Manning, Alberta in challenging winter conditions. The project was comprised of seven significant watercourse crossings and was completed using automated welding and coating processes. The pipe was a combination of GR483, GR550 and GR690 steel pipe. 

Contact Surerus:

HEAD OFFICE: 250.785.2423
ALBERTA OPERATIONS: 403.930.1358

For General Inquiries:This email address is being protected from spambots. You need JavaScript enabled to view it.

FULL CONTACT INFO & MAP

linkedinsymbol

googlepluslogo

complyworksISN LOGOcorcwb certISO bW